Bridging in a silo with a capacity of 9000 m3 (20 m high, 6m diameter). Approximately 15% of the material stored was clogged.
Sodium carbonate
To empty the silo in order to recover 100% of the storage capacity.
The customer recovered all of its storage capacity. Production was not stopped and the intervention took place in complete safety and without human intervention inside the storage unit.