airchoc

Leader in the cement industry

PROBLEM:

Build ups in the preheating tower at the: kiln inlet, smoke box, riser duct and bypass which require 8 hours’ cleaning per day (high pressure and Cardox)

OBJECTIVE:

Eliminate concretion that affect the industrial process and reduces the production capacity

Fabricant canon à air nettoyage industriel

SOLUTION:

Installation of 85 AIRCHOC® DN150 air cannons with remote solenoid valves and 2 MACSYS.

RÉSULTAT :

100% satisfaction:

  • No more build up
  • Increased use of alternative fuels
  • Rapid return on investment